Burnt Bridge Creek Diversion Pump Station

Vancouver, Washington

Owner: City of Vancouver

Client Name: Olympic Western Company

Engagement Scope

The Sutor Group was engaged by Olympic Western Company to prepare a request for equitable adjustment. Our request quantification totaled $627,261.

Project description

The contract work scope included the construction of a pump station and diversion structure.

Entitlement issues

Changed site conditions.

Type of impacts

Labor and equipment impacts relating to the changed soil conditions. Extended contract performance costs.