Kootenai Cutoff Through Colburn, Sandpoint and Clark Fork

Bonner County, Idaho

Owner: State of Idaho Transportation Department

Client Name: State of Idaho

Engagement Scope

The Sutor Group was engaged by the State of Idaho Office of the Attorney General to analyze a delay claim presented to the State from the M.A. DeAtley Construction Company.

Project description

The contract work scope included the grading, drainage and plant mix paving of 7.05 miles of US-95 and the crushing, screening, and stockpiling of anti-skid materials.

Entitlement issues

The contractor alleged that the additive change orders to the contract caused certain delays to the project and that no compensation for field or home office overhead was included in the agreed to changes.

Type of impacts

Both field and home office overhead.