Owner: Tacoma Public Utilities Water Division
Client Name: RCI Construction Group
The Sutor Group was engaged by Robison Construction, Inc. to prepare damages analysis that was submitted to its pipe and coatings supplier. The total impact damage claim totaled approximately $900,000.
The project consisted of 20,000' of 48" and 10,000' of welded steel 60" water transmission main. It also included 780' of 60" diameter micro tunnel under the Puyallup River and mainline Burlington Northern and Union Pacific Rail lines.
The owner specified coating system used on the welded steel 60" water transmission line failed.
RCI was spent labor, material and equipment dollars reworking and reapplying the failed coating system. In addition, while the owner was re-designing the solution RCI lost time and was delayed.