Owner: City of Bonney Lake
Client Name: Hartford Accident and Indemnity Company
The Sutor Group was engaged by Clevco's surety, Hartford Accident and Indemnity Company, to prepare a quantification of damages with respect to various changes that occurred on the project. The total impact based on our analysis was $550,300.
This project involved furnishing the necessary materials, labor, and equipment for installing 11,400 LF of 18", 1,900 LF of 12" and 3,900 LF of 10" main line interceptor, completing various connections to the main line interceptors consisting of approximately 1,000 LF of 8" side sewers, and a timber pile supported structural steel bridge assembly crossing a flume for support of an 8" ductile iron force main.
Defective specification relating to 18" pipe and compaction. Defective owner inspection systems.
The contractor experienced additional labor, equipment, material and subcontract costs resulting from repairs required on the project. These additional repairs resulted in the delay of the project, causing the contractor to incur extended contract performance costs for field and home office overhead.