Church Lake Interceptor, Schedule C

Pierce County, Washington

Owner: City of Bonney Lake

Client Name: Hartford Accident and Indemnity Company

Engagement Scope

The Sutor Group was engaged by Clevco's surety, Hartford Accident and Indemnity Company, to prepare a quantification of damages with respect to various changes that occurred on the project. The total impact based on our analysis was $550,300.

Project description

This project involved furnishing the necessary materials, labor, and equipment for installing 11,400 LF of 18", 1,900 LF of 12" and 3,900 LF of 10" main line interceptor, completing various connections to the main line interceptors consisting of approximately 1,000 LF of 8" side sewers, and a timber pile supported structural steel bridge assembly crossing a flume for support of an 8" ductile iron force main.

Entitlement issues

Defective specification relating to 18" pipe and compaction. Defective owner inspection systems.

Type of impacts

The contractor experienced additional labor, equipment, material and subcontract costs resulting from repairs required on the project. These additional repairs resulted in the delay of the project, causing the contractor to incur extended contract performance costs for field and home office overhead.