Owner: Weyerhaeuser Company
Client Name: Weyerhaeuser Company
Weyerhaeuser engaged us to assist their project management team in the evaluation of a claim, totaling $18,430,338, received from Casey Industrial, Inc. (Casey) relating to the construction of an OSB plant in Heaters, West Virginia.
The project involved the construction of an OSB plant including earthwork, underground utilities, buildings, equipment and roadways.
Increase concrete quantities, site contractor delays, late and conflicting design, differing site conditions, numerous change orders.
Project acceleration, labor inefficiency, extended overheads for field and home office, project delay, loss of incentive bonus, disruptions caused by numerous RFI and other requests.